The Noida International Airport, also known as Jewar Airport, is currently under construction and is projected to become the largest airport in India and Asia. The airport is located in Jewar, Gautam Buddha Nagar district, Uttar Pradesh, and will serve the National Capital Region as an alternative airport to the Indira Gandhi International Airport. Initially planned in 2001, the airport has faced several delays due to its proximity to Delhi's IGI Airport and construction challenges. The current expected completion date is May 2025, with domestic flight operations commencing on May 15 and international flights by June 25. The airport is designed to handle 12 million passengers annually in phase 1, with plans to expand to 60-120 million by 2050. The development of the airport has spurred residential and industrial growth in the surrounding areas, making it a significant infrastructure project for Western Uttar Pradesh.
| Characteristics | Values |
|---|---|
| Original deadline | 29 September 2024 |
| Revised deadline | April 2025 |
| Third revised deadline | 15 May 2025 |
| Fourth revised deadline | 25 June 2025 |
| Daily penalty | Rs 10 lakh |
| Cause of delay | Construction of the terminal building |
| Construction contract awarded to | Tata Projects |
| Number of workers deployed on-site | 8,000 |
| Expected to become | The largest airport in India and Asia |
Explore related products
What You'll Learn

The airport is expected to be operational by May 15, 2025
The Noida International Airport, also known as Jewar Airport, is expected to be operational by May 15, 2025. The airport is currently under construction in Jewar, Gautam Buddha Nagar district, Uttar Pradesh, India. With a projected capacity of 12 million passengers annually in phase 1, it is set to become the largest airport in India and Asia. The airport will serve the National Capital Region and act as an alternative airport to the Indira Gandhi International Airport.
The development of the airport has experienced delays, with the original deadline set for September 29, 2024, which was then pushed to April 2025. The delay is mainly attributed to the intricate design of the terminal building's iron façade, which resembles the ghats of Varanasi and Haridwar. The construction contract was awarded to Tata Projects in June 2022, and they are working to accelerate the pace of work by increasing manpower and deploying more machinery.
The airport is expected to boost the local economy and attract many industrial and multinational companies to establish their offices nearby. The Uttar Pradesh government also plans to build an Aerotropolis near the airport, which will include a dynamic innovation and technology hub, commercial centres, a robust logistics hub, hospitality options, and recreational and entertainment areas.
The National Highway Authority of India (NHAI) is also working on several projects to improve connectivity to the airport, including an 8.2 km road and a rapid rail-cum-metro rail corridor. The NCR Transport Corporation (NCRTC) is planning to connect the airport with the RRTS network, with a corridor spanning over 72 km.
The airport is likely to begin operations with six aerobridges, and it will be interesting to see the impact it has on the region's growth and development once it becomes operational by the expected date of May 15, 2025.
Phoenix Sky Harbor: A Sprawling Desert Airport Hub
You may want to see also
Explore related products

The project has faced multiple delays
As of March 2025, the airport is running six months behind schedule, with the original deadline set for September 2024. The delay in completing the terminal building, specifically the upper floors designated for international passengers, is the primary reason for the postponement. The construction contract was awarded to Tata Projects in June 2022, and they have attributed the delay to the complex design and extended monsoon season.
The launch of domestic and international flights has been split due to the varied completion times for different sections of the terminal building. The airport may begin cargo operations initially, with passenger operations potentially starting in July 2025 or later. The aviation regulator, Directorate General of Civil Aviation (DGCA), will issue the aerodrome license by April 30, 2025, and the airport is expected to be inaugurated on May 15, 2025, or by the end of May.
To expedite the process, the Uttar Pradesh government has directed the concessionaire, Yamuna International Airport Private Limited (YIAL), to accelerate construction work. A daily penalty of Rs 10 lakh has been imposed, effective from January 1, 2025, amounting to Rs 3 crore per month. YIAL has been instructed to follow the contract agreement regarding delay penalties.
The Story Behind LAX Airport's Name
You may want to see also
Explore related products

The airport is being developed by Zurich Airport
The Jewar Airport, or Noida International Greenfield Airport, is being developed by Zurich Airport International AG, a Swiss company headquartered in Switzerland. The company was selected as the concessionaire for the airport's development in 2019, outbidding competitors like Adani, DIAL, and Anchorage Infrastructure Investments Holdings Limited. The airport is expected to be operational by May 2025, with domestic flight operations beginning on May 15 and international flights by June 25.
Zurich Airport International AG plans to develop a modern, user-friendly, and digital airport that combines Indian culture and hospitality with Swiss technology. The company made the highest bid per passenger, offering Rs 400.97, significantly higher than its competitors. The development of the airport is expected to cost Rs 29,560 crore, according to Shailendra Bhatia, the project's nodal officer.
The airport will be spread over 5,000 hectares when fully constructed, making it the largest airport in India and Asia. It is projected to handle 12 million passengers annually in the first phase, with a potential to grow to 60-120 million by 2050 in subsequent phases. To accommodate this volume of passengers, the airport is expected to have six to eight runways, the maximum at any airport in India.
The construction contract for the airport was awarded to Tata Projects in June 2022, and the project has faced some delays. The intricate design of the terminal building's iron façade, resembling the ghats of Varanasi and Haridwar, has contributed to these delays. Additionally, the extended monsoon season in 2024 and the impact of the COVID-19 pandemic have also affected the construction timeline. As of March 2025, the airport is running six months behind schedule, with a revised deadline of May 2025.
The development of the Jewar Airport is a significant infrastructure project for the region, expected to boost the economy and create numerous job opportunities. It will enhance the connectivity and accessibility of the National Capital Region, serving as an alternative airport to the Indira Gandhi International Airport. The project has spurred residential and industrial growth in the surrounding areas, with many companies considering establishing their offices nearby. The Uttar Pradesh government's plan to build an aerotropolis near the airport further highlights the potential for commercial and residential real estate development.
Setting Airport Extreme Password: A Step-by-Step Guide
You may want to see also

The airport is projected to become the largest in India and Asia
The Noida International Airport (NIA), located near Jewar in the Gautam Buddha Nagar district of Uttar Pradesh, is projected to become the largest airport in India and Asia. The airport is expected to handle 12 million passengers annually in its first phase, with plans to expand to 60-120 million passengers by 2050 in subsequent phases. The NIA is being developed as an alternative to the heavily trafficked IGI Delhi Airport, becoming the third commercial airport in the Delhi NCR region after IGI Delhi and Hindon Airports.
The journey to develop the NIA has been a long one, with the project first proposed in 2001 as a greenfield Taj International Aviation Hub by the then Uttar Pradesh Chief Minister Rajnath Singh. The airport has faced several delays due to shifts in location and political changes, as well as the COVID-19 pandemic. Despite these challenges, construction work on the airport began in June 2022, with the Tata Projects awarded the engineering, procurement, and construction contract. The airport is expected to be operational by May 2025, with domestic flight operations commencing on May 15 and international flights by June 25.
The NIA will be connected to several highways in the Delhi-NCR region, including the Ghaziabad–Bulandshahr–Aligarh (NH-34) and Delhi–Ghaziabad–Meerut Expressway. The airport will also be linked to the Delhi-Mumbai Expressway, providing easy access to domestic and international tourists travelling to Agra, Mathura, and Vrindavan. In addition, the NCR Transport Corporation (NCRTC) is planning to connect the airport to the RRTS network, with a 72 km long corridor connecting Ghaziabad and Noida Extension to the airport.
The development of the NIA has spurred growth in the surrounding areas, with the Uttar Pradesh government planning to build an Aerotropolis near the airport to boost the commercial and residential real estate sector. The NIA is expected to attract many industrial and multinational companies to establish their offices nearby, leading to a significant increase in job opportunities. The value of properties near the airport is also expected to appreciate, making investments more profitable for buyers.
With its modern design, user-friendliness, and incorporation of Indian culture and hospitality, the NIA is poised to become a world-class airport, providing much-needed connectivity, security, and utilities to western Uttar Pradesh.
The Luis Muñoz Marín International Airport of Puerto Rico
You may want to see also

The airport will boost the commercial and residential real estate sector
The Noida International Airport, also known as Jewar Airport, is expected to be operational by May 2025. The airport is currently under construction, with the work having started in June 2022. Once completed, the airport will serve the National Capital Region and will become an alternative airport for the Indira Gandhi International Airport.
The development of the Jewar Airport is expected to boost the commercial and residential real estate sector in the surrounding areas. The Uttar Pradesh government plans to build an Aerotropolis near the airport, which will consist of a dynamic innovation and technology hub, commercial centres, a robust logistics hub, hospitality options, and recreational and entertainment areas. The presence of an airport and the subsequent development of an Aerotropolis are likely to attract many industrial and multinational companies to establish their offices nearby, leading to an increase in job opportunities.
The value of properties located near the airport is also expected to appreciate, making investments more profitable for buyers. This has already led to the growth of residential development in the area, with many localities emerging as popular choices for those looking to purchase or rent properties. The improved connectivity and infrastructure that the airport will bring are also likely to contribute to the boost in the real estate sector.
In addition to the airport's direct impact on the real estate sector, the government's plans for an Aerotropolis and the expected influx of companies indicate that the area will become a hub for economic activity. This, in turn, is likely to further drive up demand for commercial and residential spaces, leading to a thriving real estate market. Furthermore, the airport's presence may also encourage the development of supporting industries and services, such as hospitality, logistics, and transportation, creating a diverse and vibrant economic ecosystem in the region.
Reagan National Airport: Size, Scale, and Reach
You may want to see also
Frequently asked questions
The Noida International Airport, also known as Jewar Airport, was initially set to open in September 2024 but faced construction delays. The new inauguration date is May 15, 2025, with domestic flight operations beginning on the same day and international flights by June 25, 2025.
The delay is mainly due to the terminal building lagging behind schedule. The intricate design of its iron façade, which will resemble the ghats of Varanasi and Haridwar, has affected the pace of construction.
The Jewar Airport is being developed by Zurich Airport in partnership with the Uttar Pradesh government. Tata Projects holds the engineering, procurement, and construction contract for the airport.
The airport is expected to boost the commercial and residential real estate sector in the area. It will also attract many industrial and multinational companies to establish their offices nearby, leading to an increase in job opportunities.
The airport is located near Noida expressway, and road connectivity is expected to improve soon. There are also plans to introduce city bus and electric taxi services. In terms of rail connectivity, the NCR Transport Corporation (NCRTC) is planning a metro corridor connecting Ghaziabad and Noida Extension with the airport.